New build

The Canberra knock-down rebuild checklist: approvals, asbestos, trees and footings

Every approval and check between the old house and the new one: demolition, asbestos, protected trees, Icon Water, bushfire, building approval and the engineering your certifier needs.

Cleared suburban block after demolition, with timber set-out pegs and a fenced-off eucalypt

In short

A Canberra knock-down rebuild usually runs through eight checks: the demolition exemption (no shared party wall, neighbours told in writing), an asbestos removal control plan if the house predates 1985, the loose-fill Register, protected trees, Icon Water, any bushfire conditions, the new home's planning approval or exemption, and building approval with footing and slab engineering. Build costs vary too much to quote.

Key takeaways

  • Demolishing a single dwelling is DA-exempt only if there's no shared party wall and neighbours get written information before demolition starts.
  • Built or started before 1985? Expect an asbestos removal control plan with the building approval application.
  • If a protected tree or its protection zone is affected, even a neighbour's, a tree management plan is compulsory in the DA or BA.
  • Old footings, demolition and any cut or fill change the ground, so the new house needs its own site classification.
  • There's no official data on rebuild numbers or build costs. Our engineering prices are published.

What approvals does a knock-down rebuild need in Canberra?

A knock-down rebuild in Canberra needs approval for two things: taking the old house down and putting the new one up. Between them sit checks for asbestos, trees, utilities, bushfire and heritage, usually in this order.

CheckWhat appliesWhere the rule sits
1. DemolitionDA-exempt for a single dwelling only with no shared party wall, and written information to neighbours before demolition starts. Otherwise, a DA.Planning Act exemptions (DA page)
2. Asbestos planAn asbestos removal control plan with the BA application if the house is class 1–4 (or associated class 10) and was built or started before 1985.Building Act 2004, s 26
3. Loose-fill RegisterCheck the Affected Residential Premises Register. Affected homes allow only essential work or demolition.Loose-fill asbestos program; Exempt Development Regulation s 1.16
4. Protected treesA tree management plan in the DA or BA if a protected tree, or its protection zone, may be affected. That includes a neighbour's tree.Urban Forest Act 2023
5. UtilitiesIcon Water's approval before building work starts. No work in an easement or utility protection space without the utility's written permission.Icon Water guidance; DA page
6. BushfireOn the ESA bushfire map: BAL requirements through DA conditions, or through the district controls if the home is DA-exempt.Construction Note 2026-04
7. New house planningDA-exempt only if it meets the single dwelling development controls and neighbours are informed. Otherwise, a DA.NI2025-492
8. Building approvalA BA from a licensed certifier, with footing, slab, framing, bracing and tie-down details.Building Act s 26; form AF2025-18
9. Heritage or the NCAIn a registered heritage precinct, demolition is limited. In parts of Deakin and Forrest, and on main avenues, the National Capital Authority approves works, and a BA is still needed.ACT Heritage Register; BA page

Your certifier and designer confirm which checks apply to your block.

Can you knock down a house in Canberra without a DA?

Yes, if it's a single dwelling with no shared party wall and the neighbours get written information before demolition starts. Miss either condition and the demolition needs development approval.

The party wall rule catches Canberra's red-brick duplexes, built from the 1920s and again after the war: two homes sharing one wall. Taking down one half is not exempt, and the half that stays is at risk. In a 2013 Yarralumla case reported in the Canberra Times, an attached half was left with "gaping holes in her walls" after the other half came down.

No ACT law requires a dilapidation report before demolition or excavation. Master Builders ACT says one "should be treated as essential", which is advice rather than law. A dilapidation report is a dated, photographed record of the neighbouring building's condition before work starts, from $750 + GST ($825 inc GST).

Heritage precincts

In the Garden City precincts on the ACT Heritage Register, total demolition of an identified dwelling is allowed only in exceptional cases, such as a house "so structurally unsound as to be beyond reasonable economic repair". The application must include a professional structural assessment. See older and heritage homes. Demolishing any registered place likely needs a DA, and the ACT Heritage Council can advise.

What asbestos checks come before demolition?

Two. If the house was built or started before 1985, the Building Act requires an asbestos removal control plan with any building approval application for it. And before anyone starts, check whether the house is on the loose-fill asbestos (Mr Fluffy) Register.

The Register listed 17 remaining affected homes at 8 October 2026. A home on it allows only work essential for health, safety or reasonable living conditions, or demolition. Most affected houses have already gone: the ACT Government says the vast majority have been demolished, and the remediated blocks resold and rebuilt. So a former Mr Fluffy block can be a normal rebuild site.

We check the Register before any visit. We never enter or inspect affected roof spaces or subfloors, and we don't test for asbestos. See our guide to older homes and asbestos in the ACT.

What if there's a protected tree on or next to the block?

Then the tree shapes the job. Under the Urban Forest Act 2023, a tree on private land is protected if it is 8 m or taller, has a canopy 8 m or wider, or has a trunk circumference of 1 m or more at 1.4 m above the ground. Every tree on public land is protected, including verge trees.

Inside the tree's protection zone (the canopy area, plus 2 m beyond it, plus 4 m around the trunk), digging deeper than 100 mm over 4 m² or more is prohibited groundwork. So is compacting more than 10% of the zone, which demolition machinery and stored materials can do.

Tree management plans are now compulsory in DA and BA applications where a protected tree may be affected, including one on the neighbour's side. We design footings that keep digging out of the zone, such as piers and beams in place of a slab edge. Our guide to protected trees and building in the ACT explains the rules.

What else can hold up a rebuild?

Sewer mains, bushfire mapping and, on some blocks, the National Capital Authority. Check each one early.

  • Icon Water. Its guidance says its building approval is needed before work starts, even where no planning approval is required, and footings are not permitted inside a pipe's protection envelope. We don't quote clearance distances from memory. See building near a sewer in Canberra.
  • Bushfire. If the block is on the ESA bushfire map, the DA may carry a BAL condition or need a site-specific BAL assessment by a bushfire consultant. DA-exempt homes take their BAL rules from the district development controls. We don't do BAL assessments; we design to the BAL that's set.
  • The National Capital Authority. In Designated Areas, such as parts of Deakin and Forrest and blocks on main avenues, the NCA approves works instead of a DA. A building approval is still needed.

What rules apply to the new house?

The new house is DA-exempt only if it meets the single dwelling development controls and the neighbours are informed. It then needs building approval like any new home, because there are no BA exemptions for detached houses.

RuleWhat it means for the new house
GasNo new gas network connections. The new home is all-electric.
Building codeBAs from 1 May 2026 to 30 April 2027 nominate NCC 2022 or NCC 2025, not a mix. NCC 2025 is mandatory from 1 May 2027, except for projects with a DA lodged before 1 November 2026.
Rainwater tankFor DA-exempt new homes, the controls set a tank size by block size, from no minimum on compact blocks to 5,000 L on large blocks over 800 m². Full table on our sewer and stormwater page.
InspectionsThe certifier inspects the footings before the concrete is poured, the frame before it is lined, and the finished work.
Set-out surveyThe builder can't build above damp-proof course level until the certifier has a plan signed by a registered surveyor showing position and floor levels.
Moving inThe Construction Occupations Registrar issues the certificate of occupancy and use. It is against the law to occupy the house before then.

Sources: Territory Plan E01 rule 10; ACT NCC page; NI2025-492 control 17; Building (General) Regulation ss 33–34; Building Act s 69.

What engineering does the new house need?

The certifier needs structural details to lodge the BA: footing and slab details with the "nominated founding depth and description of founding material", reinforcement and concrete strength, retaining wall details, and framing, bracing and tie-downs. That list comes from form AF2025-18, the ACT's minimum documents for house BAs.

The new house won't sit on the ground the old one was built on. Demolition leaves old footings and disturbed soil, and any cut or fill changes it again. Published new-estate site reports say the class must be reassessed after cut or fill; the same logic applies here.

Canberra's ground varies, too. The rock is often deeply and unevenly weathered, so it can be near the surface on one part of a block and metres down on another. The soil mapping for the landscape most suburbs sit on notes "a considerable range in profile form occurs within a small area". No ACT law names a geotechnical report, so we write footing design for your site's soil, and we arrange a soil test at cost when the design needs one.

How much does a knock-down rebuild cost in Canberra?

We can't give you a build cost: there's no official Canberra data on rebuild costs or numbers, and builders price the build. Here is what the engineering costs.

Engineering for a rebuildFrom, ex GSTInc GST
Footings, slabs and site classification (soil test at cost)$1,290 + GST$1,419
Retaining wall engineering$890 + GST$979
Footing design near a sewer or stormwater main$790 + GST$869
Dilapidation report on a neighbouring home$750 + GST$825
Full structural design for the new houseFixed quote from your plans

Starting prices for a typical house. Your fixed quote confirms the price before we start, and says if a site visit is needed.

News reports say owners commonly knock down 1960s ex-govvies. If you're weighing up renovating against rebuilding one, our guide to renovating an ex-govvie covers the other path.

When should you call a structural engineer?

Call once you have a house design, or earlier if the block has a protected tree, a sewer main, a slope or an attached neighbour. Each one changes the footing design.

Weston Creek, for example, has many rebuilt homes beside its 1970s houses, some replacing homes lost in the 2003 fires and some on remediated Mr Fluffy blocks. See structural engineering in Weston Creek.

We're engineers only. We don't demolish, build or recommend builders, so the design isn't written around anyone's contract. Send your plans, add up to 5 files, and we reply with a fixed quote in under 20 minutes on average, during business hours.

Sources

  1. ACT Government, Check if you need a DA. Accessed 6 November 2026
  2. ACT Government, Check if you need a BA. Accessed 6 November 2026
  3. Building Act 2004 (A2004-11), ACT Legislation Register. Sections 26 and 69
  4. Building (General) Regulation 2008 (SL2008-3), ACT Legislation Register. Sections 33 and 34
  5. Single dwelling housing development controls (NI2025-492), ACT Legislation Register. Accessed 6 November 2026
  6. Approved form AF2025-18, minimum documents for class 1 and 10 building approvals, ACT Legislation Register. Approved 15 September 2025
  7. ACT Government, Loose-fill asbestos: affected properties. Register as at 8 October 2026
  8. ACT City Services, Tree protection laws. Accessed 6 November 2026
  9. Access Canberra, Construction Note 2026-04: Bushfire Attack Level requirements (PDF). Accessed 6 November 2026
  10. ACT Government, National Construction Code. Accessed 6 November 2026
  11. ACT Heritage Register, Reid Housing Precinct entry (PDF). Clause 5.1a, demolition
  12. Master Builders ACT, Why dilapidation reports matter. Industry advice, not law

Knock-down rebuild questions

Something else on your mind? Call 02 6189 9876, email info@canberrastructuralengineers.com.au or send photos for a fixed quote.

Do I need approval to demolish a house in Canberra?

Not always a DA. Demolishing a single dwelling is exempt from development approval if it shares no party wall with another home and the neighbours get written information before demolition starts. Your certifier tells you what else the demolition needs, including an asbestos removal control plan for a house built or started before 1985.

Can I knock down one half of a duplex?

Not under the demolition exemption. The exemption needs no shared party wall, so plan for development approval. The attached half is the main risk: a dilapidation report records its condition first, from $750 + GST ($825 inc GST).

Do I need a new soil test for a knock-down rebuild?

Usually, yes. No ACT law names a geotechnical report, but your certifier has to lodge the founding depth and a description of the founding material, and demolition, old footings and any cut or fill change the ground. We arrange a soil test at cost when the footing design needs one.

How much does a knock-down rebuild cost in Canberra?

There's no official Canberra data on build costs, so we don't quote one. Our engineering prices are published: footings, slabs and site classification start from $1,290 + GST ($1,419 inc GST), and the full structural package for the new house is a fixed quote from your plans.

Do you do the bushfire (BAL) assessment?

No. A site-specific BAL assessment is a bushfire consultant's job. We design the structure to the BAL your consultant or the development controls set.